June 2011

June 2011

Long Creek Watershed Management District Spring Update

Long Creek Watershed Management District Spring 2011 Update

June 2011

In this issue

 

Based on the data collected during 2010 as well as feedback received from DEP and other stakeholders, we have been busy developing the best approach to meet the requirements of the Long Creek Management Plan going forward.    The following summarize the work we have been doing since the beginning of the year.

 

Winter Maintenance Round Table (7/28)

This year LCWMD is focusing on winter maintenance and its effects on water quality.  To kick off this initiative, we are hosting the Winter Maintenance Round Table on July 28th from 2-4 pm at the Sable Oaks Marriott.  We are looking forward to meeting with property owners, operators, managers, and their winter maintenance contractors to develop tracking mechanisms, pilot-scale programs, and best management practices to minimize the effects of deicers on water quality in Long Creek.  Invitations will be sent out in early July.  Please RSVP by July 22 to kmcdonald@cumberlandswcd.org. 

 

Pollution Prevention & Good Housekeeping
Operation and Maintenance Plans were sent out to each landowner in March.  Each plan provides the list of inspection and maintenance activities required for each parcel.  LCWMD is conducting street sweeping, catch basin & storm drain cleaning, and maintenance of any of its own BMPs. LCWMD is also inspecting each parcel for those landowners who have not elected to hire their own inspector and apply for credit.  Inspections will occur in July and August, and each property owner will be notified of any maintenance activities that are identified during the inspection. 
 

Spring Cleanup:  Street Sweeping

Over the past two months, we have completed the spring cleanup vacuum sweeping on all of the parcels.  We collected 217.98 tons of material during the spring sweep, and over the next two weeks we expect to complete the corner-to-corner sweepings (74.27 tons of material collected to date), and we will conduct additional "hotspot" sweeping in July for those parcels that have it identified in their Operation & Maintenance Plans.

Catch Basin Cleaning

Catch basins were cleaned during fall 2010 and 26.93 tons of material was removed.  The 2011 summer catch basin cleaning will be occurring beginning during the week of July 4. 

Monitoring

Late in 2010 DEP provided comments on the Quality Assurance Project Plan (QAPP), which provides the data collection and quality requirements for the Long Creek project.  The QAPP and Monitoring Plan were both revised to address DEP's comments as well as incorporate some of the lessons learned from the 2010 sampling season.  Both documents received provisional approval in March and implementation began with the spring sampling on March 24.  DEP approved the revised QAPP and Monitoring Plan in April. 

Spring Monitoring Program

The spring monitoring program began on March 24 and included 4 weekly runoff sampling events and monthly sampling in May and June.  Samples were collected for targeted analytes depending on their locations and likelihood of containing specific compounds.  To date all data through May has been received from the laboratory and is in the process of being compiled into an electronic database.  The data will be analyzed at the end of the monitoring season to determine if further revisions to the monitoring plan are necessary.

Monitoring Contractor Selection

The surface water monitoring program was put out to bid in February and a contractor was selected and the contract was approved by the LCWMD Board in May.  URS Corporation will begin surface water monitoring, weather data collection and data management activities on July 1.  LCWMD appreciates all FB Environmental's hard work on getting the monitoring program off to a successful start in 2010 and providing a good basis for ongoing monitoring.

Academic Research Partners Update

The University of Southern Maine is currently conducting two research projects in the watershed:  Dr. Lucille Benedict is evaluating the chemical components of street dust and its effect on stream sediments.  Dr. Karen Wilson is using automated samplers at two locations to evaluate water quality over time.

 

 For more information about any of these topics,visit the Long Creek Restoration Project Website.

Long Creek Watershed Management District,c/o Cumberland County Soil and Water Conservation District,35 Main St Suite 3, Windham, ME 04062

 

 

 

 
Posted in: General News 
Post Date: Wednesday, February 24, 2016 12:21 PM